Overview GANTT
Commissioning Gantt
Commissioning Data
EMS, Sea Trial and Post Handover

Commissioning Schedule

AWP • Waste • EAP — June 2026 to March 2027

Note: This timeline shows estimated activity durations, not confirmed execution dates. Exact scheduling is subject to coordination with the yard and may change.

AWP
WASTE
EAP

Full Project Gantt Chart

All three systems — June 2026 to March 2027

* Durations are indicative. Actual execution dates to be confirmed with the yard.

AWP System

Advanced Wastewater Purification — 215 days

* Durations are indicative. Actual execution dates to be confirmed with the yard.

Waste System

Waste Processing & Treatment — 242 days

* Durations are indicative. Actual execution dates to be confirmed with the yard.

EAP System

Energy & Advanced Processing — 223 days

* Durations are indicative. Actual execution dates to be confirmed with the yard.

EMS, Sea Trial and Post Handover

All Systems

Note: Durations are indicative and subject to coordination with the yard. Headcount (👤) is the number of people each company sends for that activity.

Activity
Scanship
Specialist
Automation

Personnel by Company

Activity Schedule — All Systems (data from Smartsheet export)

# Task Team Start Date End Date Duration People

* Durations are indicative. Actual execution dates to be confirmed with the yard.

Project Overview

All Main Systems — Gantt Timeline — Jan 2026 to Oct 2027

100%

Dependencies: Phases follow predecessor relationships. Each phase starts after its predecessor completes (Finish-to-Start). Hover over bars for details.

Phase
AWP
WDE Sub-Systems
WDE Digester
EAP Onboard
EAP Test Site
EAP Pelletizer
Dependency
Contingency (if preapproval fails)
Optional

Activity Schedule

# Activity / Phase Duration Start End Predecessor

* Durations are indicative. Actual execution dates to be confirmed with the yard.