Overview GANTT
Commissioning Gantt
Commissioning Data
Test Site Gantt
EMS & Sea Trial Gantt
EMS & Sea Trial Data

Commissioning Schedule

AWP • Waste • EAP — June 2026 to March 2027

Note: This timeline shows estimated activity durations, not confirmed execution dates. Exact scheduling is subject to coordination with the yard and may change.

AWP
WASTE
EAP

Full Project Gantt Chart

All three systems — June 2026 to March 2027

* Durations are indicative. Actual execution dates to be confirmed with the yard.

AWP System

Advanced Wastewater Purification — 215 days

* Durations are indicative. Actual execution dates to be confirmed with the yard.

Waste System

Waste Processing & Treatment — 242 days

* Durations are indicative. Actual execution dates to be confirmed with the yard.

EAP System

Energy & Advanced Processing — 223 days

* Durations are indicative. Actual execution dates to be confirmed with the yard.

Test Site Gantt Plan

Cyclone & Gas Pipe — Manufacturing, Installation & Testing — May–June 2026

Dependencies: Activities follow predecessor relationships as defined. Delays in any activity may cascade to dependent activities.

Activity
Manufacturing
Installation
External Test
Retrofitting
Preapproval
Dependency

Activity Schedule

# Activity Duration Start End Predecessor
1 Manufacturing of cyclone 10d 04.05.26 15.05.26
2 Manufacturing of extended Gas pipe 15d 04.05.26 22.05.26
3 Installation of Cyclone 3d 18.05.26 20.05.26 FS → #1
4 Installation of Extended Gas Pipe 6d 25.05.26 01.06.26 FS → #2
5 External Testing of the Cyclone 10d 01.06.26 05.06.26 FS → #2, #1
6 Retrofitting to Internal Cyclone 5d 08.06.26 12.06.26 FS → #5
7 Preapproval PL2 Dry Garbage 4d 15.06.26 18.06.26 FS → #6
8 Preapproval PL2 Bio Waste 2d 19.06.26 22.06.26 FS → #7

Reactor Test Site

Including Pelletizer Test Site — live copy of the Overview section, fully editable

Activity

EMS & Sea Trial

All Systems — March 21 to April 6, 2027

Note: All activities run in parallel during the sea trial period. Durations are indicative and subject to coordination with the yard.

Activity
Scanship
Specialist
Automation

EMS & Sea Trial — Activity Schedule

All Systems — data from Smartsheet export

All Systems — Sea Trial

# Task Team Start Date End Date Duration

* Durations are indicative. Actual execution dates to be confirmed with the yard.

Project Overview

All Main Systems — Gantt Timeline — Jan 2026 to Oct 2027

100%

Dependencies: Phases follow predecessor relationships. Each phase starts after its predecessor completes (Finish-to-Start). Hover over bars for details.

Phase
AWP
WDE Sub-Systems
WDE Digester
EAP Onboard
EAP Test Site
EAP Pelletizer
Dependency
Contingency (if preapproval fails)
Optional

Activity Schedule

# Activity / Phase Duration Start End Predecessor

* Durations are indicative. Actual execution dates to be confirmed with the yard.